Notice Requesting Public Comment on Draft Air Quality Construction and Operation Permits for Miller & Long - EIN Presswire

2022-08-26 20:49:15 By : Mr. Steven Pan

There were 1,370 press releases posted in the last 24 hours and 218,276 in the last 365 days.

PUBLIC NOTICE Notice Requesting Public Comment on Draft Air Quality Construction and Operation Permits for Miller & Long Co., Inc. – 5300 South Dakota Avenue NE Site

Notice is hereby given that, pursuant to 20 DCMR § 210, the Air Quality Division (AQD) of the Department of Energy and Environment (DDOE), located at 1200 First Street NE, 5th Floor, Washington DC, intends to issue p ermit Nos. 7333 through 7337 to Miller & Long Co., Inc to operate two (2)  concrete batch plants and three (3)  non-emergency generator sets, powered by diesel-fired engines, to be located at 5300 South Dakota Avenue NE, Washington DC.

CEMCO 275 Truck Mix Concrete Plant

ELBA EMC85VAS Central Mix Concrete Plant

One factory mounted (CEMCO) generator set powered by a 173 hp John Deere diesel engine, Engine Family BJDXL06.8116 (Model year 2011)

One MQ Power WhisperWattTM, Model DCA400SSI4F3, 320 kWe prime/336 kWe standby generator set powered by an Isuzu Model BQ-6WG1X 512.3 hp (382 kWm) Diesel Engine (Model year 2020)

One MQ Power WhisperWattTM, Model DCA400SSI4F3, 320 kWe prime/336 kWe standby generator set powered by an Isuzu Model BQ-6WG1X 512.3 hp (382 kWm) Diesel Engine (Model year 2021)

The contact person for the facility is Paul MacDonald at (302)-215-1029 or [email protected] .

The applicant has requested that enforceable limitations on the operation of the portable concrete plants and non-emergency generator sets be established in the permit pursuant to 20 DCMR § 201. Specifically, the applicant has requested an operating hour limit for all equipment at the site of 3,744 hours per unit per 12-month rolling period. Limits on the concrete production rate of 275 cubic yards per hour and 1,029,600 cubic yards in any consecutive 12-month period per plant have also been requested for Plant #1 and 109 cubic yards per hour and 408,096 cubic yards in any consecutive 12-month period for Plant #2.

Factoring in these operational limits, the following is an estimate of the overall potential emissions from the facility:

FACILITY-WIDE EMISSIONS SUMMARY [TONS PER YEAR]

With the operational limitations included in the draft permit, the Miller & Long Co. facility has the potential to emit approximately 4.23 tons per year of oxides of nitrogen (NOx), which is below the District’s major source threshold of 25 tons per year of NOx. Similarly, all other pollutants’ potential emissions are below their respective major source thresholds. As such, the facility is properly classified as a minor source and is not subject to 20 DCMR § 300.1.

The following units are being permitted through this permitting action. After each table of units, the proposed emission limits are specified.

Portable Concrete Mixing Plants: Two (2) portable temporary portable concrete plants with an associated boiler with a heat input rating of 3.5 MMBTU per hour:

Production Rate (cubic yd/hr)

a.   Emissions of dust shall be minimized in accordance with the requirements of 20 DCMR 605 and the “Operational Limitations” of this permit.

Non-Emergency Generator Sets Powered by Compression Ignition Internal Combustion Engines (CI-ICE) subject to New Source Performance Standards (NSPS): Four (4) non-emergency generator sets powered by diesel-fired engines subject to NSPS (40 CFR 60) Subpart IIII as described in the following table:

One factory mounted (CEMCO) generator set powered by a 173 hp John Deere diesel engine, Engine Family BJDXL06.8116 (Model year 2011)

One MQ Power WhisperWattTM, Model DCA400SSI4F3, 320 kWe prime/336 kWe standby generator set powered by an Isuzu Model BQ-6WG1X 512.3 hp (382 kWm) Diesel Engine (Model year 2020)

One MQ Power WhisperWattTM, Model DCA400SSI4F3, 320 kWe prime/336 kWe standby generator set powered by an Isuzu Model BQ-6WG1X 512.3 hp (382 kWm) Diesel Engine (Model year 2021)

Pollutant Emission Limits (g/kW-hr)

DOEE has reviewed the permit applications and related documents and has made a preliminary determination that the applicant meets all applicable air quality requirements promulgated by the U.S. Environmental Protection Agency (EPA) and the District. Therefore, draft permit Nos 7333 through 7337 have been prepared.

The permit applications and supporting documentation, along with the draft permits are available for public inspection at AQD and copies may be made available between the hours of 8:15 A.M. and 4:45 P.M. Monday through Friday. Interested parties wishing to view these documents should provide their names, addresses, telephone numbers and affiliation, if any, to Stephen S. Ours at (202) 535-1747. Copies of the draft permit and related technical support memorandum are also available at http://doee.dc.gov/service/public-notices-hearings.

A public hearing on this permitting action will not be held unless DOEE has received a request for such a hearing within 30 days of the publication of this notice. Interested parties may also submit written comments on the permitting action. The written comments must include the person’s name, telephone number, affiliation, if any, mailing address and a statement outlining the air quality issues in dispute and any facts underscoring those air quality issues. All relevant comments will be considered in issuing the final permit.  

Comments on the draft permits and any request for a public hearing should be addressed to:  

Stephen S. Ours   Chief, Permitting Branch - Air Quality Division

Department of Energy and Environment 1200 First Street NE, 5th Floor Washington, DC 20002

No comments or hearing requests submitted after September 19, 2022 will be accepted.

For more information, please contact Stephen S. Ours at (202) 535-1747 or [email protected] .

EIN Presswire's priority is source transparency. We do not allow opaque clients, and our editors try to be careful about weeding out false and misleading content. As a user, if you see something we have missed, please do bring it to our attention. Your help is welcome. EIN Presswire, Everyone's Internet News Presswire™, tries to define some of the boundaries that are reasonable in today's world. Please see our Editorial Guidelines for more information.